This Month’s Projects – June 2013

This month installation works at Birmingham continued with another four gantries being installed on site, while a fifth gantry was taken down and transported back to Nusteel on the M4/M5 project for refit.  The additional stairs for the Port Talbot project (as mentioned last month) were also installed for Costain who commented “Thanks for another… Read more

This Month’s Projects – May 2013

This month following the completion of the new gantry structures, works have begun on refurbishing several existing gantries on the M4/M5 project.  This included the dismantling and transportation back to Nusteel’s works of four gantries for a full refit.   Meanwhile another team were busy installing a Footbridge and Ramps at Port Talbot in Wales (as… Read more