We have been pushing hard on gantry installations this month with our site teams busy on the A19, M1 and M4. A variety of different design types continue to be manufactured with Non-Access and Full-Access portals, ADS and MS4 Cantilevers being installed throughout the UK during January and February.
On the M1 J13-J16, our site teams are making the most of the road closures installing 3 structures at the same time. This reduces the number of road closures, saving costs for the project and lessening the disruption for the road user.
![](https://www.nusteelstructures.com/wp-content/uploads/M4_2-Feb-21-Edit.jpg)
![](https://www.nusteelstructures.com/wp-content/uploads/M4_3-Feb-21-Edit.jpg)
![](https://www.nusteelstructures.com/wp-content/uploads/M4-Feb-21-Edit.jpg)