Sign Gantries going up! – February 2021

We have been pushing hard on gantry installations this month with our site teams busy on the A19, M1 and M4. A variety of different design types continue to be manufactured with Non-Access and Full-Access portals, ADS and MS4 Cantilevers being installed throughout the UK during January and February.

On the M1 J13-J16, our site teams are making the most of the road closures installing 3 structures at the same time. This reduces the number of road closures, saving costs for the project and lessening the disruption for the road user.